Building Blackwater: Q1 2024 Project Update

    [Music]
    key objectives for the construction team
    during quarter 1 20124 was to progress
    the transmission line Construction Works
    establish the mine Creek and Davidson
    Creek cut off changes in this tailing
    storage facility whilst progressing the
    process facility Civil Works and
    commence the electrical installation
    works in the process facility we have
    finished the clearing and we’ have
    started the installation of the poles to
    bring the power to the Blackwater mine
    most of the electrical gear is already
    on site we got Transformers ready to be
    installed so it’s very exciting stage
    the team has made great progress we’re
    well Advanced and where we need to be at
    this time of the project development
    they’re problem solvers and they’re
    exceptional we’ve had a lot of major
    highlights for the quarter we are
    currently hydrotesting our tanks we’ve
    put up the gravity concentrators we’ve
    put up the gravity Tower structural
    steel we’ve installed the Kiln into the
    ADR completed all the pre-eng steel for
    the re agent building as well as putting
    in the overhead crane we’ve also managed
    to construct a large portion of the
    conveyors placed in the feeders for the
    reclaim tunnel got the ball mill shells
    completed the ends on as well as getting
    the pregnant solution tanks and also a
    filter press installed in the Gold Room
    as well in q1 we have completed the two
    6040 shovels and five 713 Hall trucks
    whilst maintaining the availability to
    the Earthworks Fleet
    we’re near completion of the CDs the wmp
    is near completion the West BM is built
    and we be lined next week we were able
    to make huge Headway in the tsf we’ve
    built the access road into the Ops Camp
    the Ops Camp pad itself will be complete
    here next week in the first quarter of
    2024 we saw the Peak Workforce Manning
    during the second quarter of this year
    we expect to maintain that Manning
    throughout all areas of the build what
    was pleasing to see
    was the team’s impressive safety record
    here on site just over 1.5 million man
    hours completed LTI 3 I’m proud to say
    that 20% of our team here at site are
    women and we’re drawing from the
    community 30% come from the indigenous
    communities around us and around 80% are
    from within BC it’s a friendly
    environment you can walk down the
    hallway and you can talk to anyone it’s
    a nice atmosphere we commenced
    establishing the operations team here at
    Blackwater and at quarter 1 we’re on
    track for first GOP in H2 2024

    Overall construction at the Blackwater Mine was ~73% complete at the end of Q1, 2024. The project remains fully funded, within the guidance for initial capital expenditure, and on schedule for first gold pour in the second half of 2024. Watch to hear from our team about progress made in Q1 and find more details in our media release: https://artemisgoldinc.com/news/media-releases/2024/artemis-gold-provides-q1-update-on-blackwater-mine-construction-progress